- 'Commercial Operation' signifies that the Initial Operation, Reliability Run and Performance Tests have been successfully completed for the Nuclear Power Plant. The Owner shall separately test, take over each unit, together with the system and subsystems directly related thereto and the remaining unit.
- 'Commissioning' is period of testing and measurements starting with initial fuel loading and power raising in which the performance of the Plant is demonstrated with regard to startup, shutdown, part-load operation, load changing capabilities, and all other modes of operation and is concluded by continuous 24-hour Performance Test.
- 'Completion of the Contract' means the issue of the last Final Acceptance Certificate.
- 'Completion of the Works' means that all of the Works have been taken over by the Owner.
- 'Construction Equipment/Plant' means all appliances or things of whatsoever nature required in or about the execution, maintenance or completion of the Temporary Works (as hereinafter defined) and execution and completion of the Works but does not include materials or other things intended to form or forming part of the Permanent Works.
grup : batanppen, jakarta, matematika, visual basic, adsense, internet, online, bisnis
Tidak ada komentar:
Posting Komentar