- Engineer/Consultant/Representative is person or an organization or its representative as may be appointed by the Owner, to assist and support him in technical, commercial or legal matters. Such Consultant or Representative shall have no direct relations or controlling interest in firms which manufacture and supply fuel. The duties and authority of the engineer may include the following:
1. to watch and supervise the works to ensure that the works are carried out in accordance with the contract.
2. to give the instruction and direction as the work proceed,
3. to give the approval and/or comments on information and documents submitted by the Contractor.
4. to carry out other duties to be stated in the contract
- 'Final Acceptance Certificate' means the certificate issued by the Owner to the Contractor, at the end of the Warranty Period.
- 'Final Contract Price' means the aggregate of :
- the Total Contract Price;
- the amounts of increase or decrease payable to the Contractor in accordance with Clause 47 (Variations) herein;
- the amounts payable to the Contractor in respect of work performed on Force Account basis in accordance with Part 3, Clause 1; subject to the deduction of any monies due to the Owner by the Contractor in accordance with the Contract.
- Final price is the price to finally paid to the Contractor and being the contractual price, adjusted as provided by the fuel contract.
- Final takeover is take over the plant by the Owner at the end of Guarantee Period.